Lead A School

27 tasks

The ultimate perceived and actual quality of the school—improved performance, engagement, pride, satisfaction, equity, well-being, and reduced wasted effort. (Coherence that produces results for all.)

Start this plan

Sign in to review and change this plan before creating a private project.

Derived from guideLead A School
Source details

Derivation tier: T1

lead-a-school · fd83eaa4537316fb4613012fbfbd2f6ac7f5bbb41bdc0dc085a7d51ca1ab076d

Authorship and review status are not recorded here.

Template tasks (27)

Review tasks and choose or change owners before creating your project. Assigning an agent does not start it.

Tasks begin as To Do in your project.

  • #1Moral Purpose & Leader ResponsibilityMedium

    Clarifies what it means to hold yourself—not demographics, funding, or district policy—as the variable that determines whether your students thrive.

    Completion check

    The moral purpose & leader responsibility work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 0 days after project start · Planned duration: 7 days

  • #2Leader Personal AttributesMedium

    Names the personal characteristics that amplify—or blunt—everything else you do, and treats them as trainable disciplines rather than fixed traits.

    Completion check

    The leader personal attributes work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 7 days after project start · Planned duration: 7 days

  • #3Contextual LiteracyLow

    Read your specific school—its history, factions, sacred cows, and latent capacity—before you act on it.

    Completion check

    The contextual literacy work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 14 days after project start · Planned duration: 3 days

  • #4Educator Subculture Alignment & ResistanceLow

    Maps the distribution of staff toward student success—Believers versus Fundamentalists—and the behavioral resistance to reform, including how new teachers (Tweeners) get pulled toward one camp. You learn to read and shift the political terrain.

    Completion check

    The educator subculture alignment & resistance work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 17 days after project start · Planned duration: 3 days

  • #5External Accountability Policy ContextLow

    Situates your school within the macro policy environment—high-stakes testing, ESSA, prior NCLB pressures—and shows how that pressure interacts with your internal change effort. You learn to use the context rather than merely absorb it.

    Completion check

    The external accountability policy context work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 20 days after project start · Planned duration: 3 days

  • #6Predetermination BaselineLow

    Names the pre-existing conditions—teacher expectations, student self-perceptions, and institutional sorting—that set how hard transformation will be before you start. You learn to diagnose your true baseline.

    Completion check

    The predetermination baseline work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 23 days after project start · Planned duration: 3 days

  • #7Change Leadership & RationaleMedium

    Make the case for change so teachers move with you rather than comply, endure, or wait you out.

    Completion check

    The change leadership & rationale work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 26 days after project start · Planned duration: 7 days

  • #8Staff Trust in LeadershipLow

    How educators come to trust your competence and character enough to follow you into change they didn't design.

    Completion check

    The staff trust in leadership work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 33 days after project start · Planned duration: 3 days

  • #9Positive Emotional Tone / FilterLow

    Address how you deliberately regulate the flow of emotion and information in the building to set its prevailing tone.

    Completion check

    The positive emotional tone / filter work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 36 days after project start · Planned duration: 3 days

  • #10Hiring & Retaining TalentLow

    Building the pipeline and conditions that let you recruit strong teachers and keep them from leaving.

    Completion check

    The hiring & retaining talent work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 39 days after project start · Planned duration: 3 days

  • #11School Culture & ClimateHigh

    Apply a working model of what actually constitutes your school's culture and climate, and where a principal can and cannot exert leverage on it. You will learn to distinguish the durable belief layer from the volatile mood layer.

    Completion check

    The school culture & climate work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 42 days after project start · Planned duration: 14 days

  • #12Collaborative Professional CultureHigh

    Define the working relationships that let teachers improve instruction together daily, and how to distinguish real interdependence from cosmetic collaboration.

    Completion check

    The collaborative professional culture work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 56 days after project start · Planned duration: 14 days

  • #13Teacher Development & Knowledge BuildingHigh

    Address how you grow teacher skill through embedded learning—modeling, observation, and shared knowledge—rather than directives and workshops.

    Completion check

    The teacher development & knowledge building work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 70 days after project start · Planned duration: 14 days

  • #14Staff Commitment, Efficacy & MoraleHigh

    Build the collective conviction that every student can learn, and how that conviction converts into discretionary effort from your staff.

    Completion check

    The staff commitment, efficacy & morale work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 84 days after project start · Planned duration: 14 days

  • #15Behavior Before BeliefsLow

    The counterintuitive sequence of changing what teachers do first and letting new convictions follow from the results they see.

    Completion check

    The behavior before beliefs work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 98 days after project start · Planned duration: 3 days

  • #16Instructional Leadership & Teacher Mind FramesLow

    Lead teacher learning while shaping the evaluative beliefs teachers hold about their own effect on students. You will learn to make impact-thinking the center of instructional leadership.

    Completion check

    The instructional leadership & teacher mind frames work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 101 days after project start · Planned duration: 3 days

  • #17Clarity of Learning GoalsLow

    Make intended learning outcomes and success criteria explicit and shared between teachers and students. It gives you the mechanics of alignment, not just goal-writing.

    Completion check

    The clarity of learning goals work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 104 days after project start · Planned duration: 3 days

  • #18Accountability & MonitoringLow

    Systems that require full participation in a change and monitor performance so that staff comfort depends on adopting the new way of working. You learn to make the new paradigm the path of least resistance.

    Completion check

    The accountability & monitoring work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 107 days after project start · Planned duration: 3 days

  • #19Coherence & Shared UnderstandingLow

    Why staff need a shared, felt understanding of the work—not just aligned documents—and how that understanding actually forms.

    Completion check

    The coherence & shared understanding work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 110 days after project start · Planned duration: 3 days

  • #20Effective FeedbackLow

    Define feedback that actually changes learning: information that closes the gap between where a student is and where they need to be, and hands control back to the learner. You will learn what to say and when it lands.

    Completion check

    The effective feedback work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 113 days after project start · Planned duration: 3 days

  • #21Appropriate Challenge SettingLow

    Address calibrating task difficulty to each student's zone of proximal development. You get the judgment calls behind pitching work at the edge of current ability.

    Completion check

    The appropriate challenge setting work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 116 days after project start · Planned duration: 3 days

  • #22Dialogic TeachingLow

    Generate classroom talk that is collective, reciprocal, cumulative, and purposeful—dialogue that builds understanding rather than checking recall. You learn to structure talk as a learning engine.

    Completion check

    The dialogic teaching work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 119 days after project start · Planned duration: 3 days

  • #23Classroom Climate of TrustLow

    Building a classroom students perceive as safe, fair, and respectful—where admitting confusion and asking for help carry no social cost. You learn what actually generates that perception.

    Completion check

    The classroom climate of trust work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 122 days after project start · Planned duration: 3 days

  • #24Student Self-RegulationLow

    Address how students activate and sustain the cognition, behavior, and emotion needed to pursue learning goals on their own. You learn to build the learner's internal management system.

    Completion check

    The student self-regulation work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 125 days after project start · Planned duration: 3 days

  • #25Teacher Effectiveness & EngagementLow

    Define effective, engaged teaching as an observable behavioral pattern—strong classroom management, quality instruction, respectful treatment of students, and influence beyond one's own room. You learn what high performance looks like in practice.

    Completion check

    The teacher effectiveness & engagement work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 128 days after project start · Planned duration: 3 days

  • #26Student Learning OutcomesHigh

    Define what counts as student success when you lead a school, and why a single test-score number distorts it. You leave with a defensible, multi-dimensional picture of outcomes you can actually steer.

    Completion check

    The student learning outcomes work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 131 days after project start · Planned duration: 14 days

  • #27Overall School Quality & Organizational OutcomesHigh

    Define what 'a good school' actually resolves to in measurable and felt terms, and how to read those signals without confusing motion for progress. It gives you the outcome frame that every other leadership decision should serve.

    Completion check

    The overall school quality & organizational outcomes work is complete: key decisions are recorded and outputs are ready for the next phase.

    Choose or change the owner during setup.

    Starts 145 days after project start · Planned duration: 14 days

Start this plan

Sign in to review and change this plan before creating a private project.

Template usage
  • Recorded uses: 0
  • Projects marked complete: 0 (self-declared)
  • Independent completion results are not available.